GMU CLOSED MONDAY SEPTEMBER 23 - SUNDAY OCTOBER 13, 2024

Centreville Swim Club

Our last practice at GMU will be Sunday, September 22nd. GMU will reopen Monday, October 14th. All Sunday practices will be at Manassas Park. While GMU is closed please join us at Cub Run or Manassas Park

Cub Run Practice Schedule- Cub Run RECenter 4630 Stonecroft Blvd, Chantilly, VA 20151

13 & Over - Monday, Wednesday, Friday - 6:15 am - 7:15 am

13 & Over - Tuesday, Thursday - 6:00 am - 7:15 am

Middle School - Monday, Tuesday, Wednesday, Friday - 3:00 pm - 4:00 pm

12 & Under - Monday - Thursday - 7:15 am - 8:15 am

Manassas Park Practice Schedule - Manassas Park Community Center, 99 Adams Street, Manassas Park, VA 20111

13 & Over - Monday - Friday - 5:30 am - 7:00 am

12 & Under - Monday - Thursday - 6:00 am - 7:00 am

12 & Under - Monday - Thursday - 5:00 pm - 6:00 pm

All ages - Sunday - 3:00 - 4:00 pm - Only while GMU is closed

GMU TIMELINE:

 This timeline is based on no issues, and GMU will let us know as soon as possible if it needs to be adjusted.  

  • 09/23 - GMU will begin to drain pool at 5am
  • 09/30 - 10/06 - "T" repair and sand/filter repairs will  take place
  • 10/07 - GMU will begin re-filling the comp pool after work to retrofit the missing ‘Ts’ is complete. 
  • The process for re-filling the pool will take a minimum of 72-hours, which means that the bulkheads can’t be installed until 10/10. 
  • 10/08 - Both bulkheads will ship from manufacturer on 10/03 and will take five days to arrive onsite.   
  • 10/10 – Bulkheads will be placed in the comp pool. 
  • 10/10 - 10/13 - Bulkhead install and water rebalancing will take place
  • 10/14 - Competition pool will re-ope